On March 16, 2024, the Uganda National Roads Authority (UNRA) announced the commencement of repair works on one lane of the Kireka-Namugongo road in Kampala. This decision follows a public notice issued by UNRA on March 12, 2024.
The purpose of these maintenance works, according to UNRA, is to improve the road’s surface condition and safety. The aim is to ensure satisfaction and comfort for all users of the road. The repair works are scheduled to conclude by the end of May 2024.
UNRA outlined the scope of the physical works, which include resurfacing the main carriageway and installing road safety facilities. During the repair period, traffic will be restricted to one lane, while the other undergoes maintenance. Additionally, certain sections of the road will experience temporary closure during Asphalt concrete overlay operations. In such instances, traffic will be redirected to nearby alternative routes. To aid road users, both the Traffic Police and the contractor’s safety team will be present on-site to provide assistance.
It’s worth noting that the company responsible for these repairs is Stirling, the same company currently engaged in the construction and repair of the Northern Bypass. This indicates a continuation of their involvement in infrastructure projects within the region.
Maintenance Schedule and Traffic Management
| Date | Activity | Impact on Traffic |
|---|---|---|
| March 16, 2024 | Commencement of repair works | One lane closure |
| March-May 2024 | Resurfacing of main carriageway and safety installations | Traffic restricted to one lane during repair |
| Temporary closure during Asphalt concrete overlay operations | Traffic diverted to nearby alternative routes | |
| End of May 2024 | Anticipated completion of repair works | Full restoration of road access and traffic flow |
With the cooperation of road users and the assistance provided by the Traffic Police and the contractor’s safety team, disruptions to traffic flow are expected to be minimized throughout the repair period.